Hello SAP Experts!
How do we remove the planned cost that was entered as the total amount of the Material Component after its PR has been created?
We use the planned cost from the Activities/Material Components as reference to our budgeting, but once a PR is created during release of the Network Activity containing a Material Component, the same amount is posted as commitment, the total amount for the WBS Element holding the Material Component is then doubled (planned cost + commitment amounts).
Thanks and regards,
Ramon
Hello
Try creating CO versions and copy Version XX from version 0.
PR / PO changes will reflect in version 0 only & not in version XX.
Shubham
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramon,
Where you find this value doubled, since the planned cost is converted here into commitment, both plays different role.
I mean report or transaction you are executing and seeing doubled values.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.