9999 document available to post/defer

former_member222701
Participant
0 Kudos

Hello,

Came across a contract account while posting payment and it brings up a 9999 document available to post/defer, is this standard SAP?

I did some testing with some accounts and this is what I found:

When the account has only the 12/31/9999 doc open (not other open items).  The post deferral option ends with an error message: "Error occurred for selected activity, do you want to display step log?  (Business Proc ZDEFER2-Object does not exists).

When there are other open items besides the 12/31/9999 document, regardless if it is debit/credit, it prompts you with the post deferral screen.  And of course if you enter a deferral for 12/31/9999 document, you will get an informational message stating the following: Deferral date must be after due date 12/31/9999.

Is there something in SAP configuration/development to find out if there is a setting that can be changed to gray-out the 12/31/9999 document?

3 REPLIES 3

AmlanBanerjee
Active Contributor
0 Kudos

Hi Valentina,

You can place a payment lock against the document level for the particular document.

Once done, it will not be picked for deferral with other items.

Hope it helps

Thanks,

Amlan

0 Kudos

Hello Amian,

The actual issue is when we are trying to create a deferral for an account the document number with the due date 12/31999 still pops-up and it allows us to post a deferral date and save and then we get the error message mentioned above.

Since we have to meet a quota with time and customers, we need to remove all the unnecessary steps to complete our job faster.  Is there anything in configuration/development to grey out the document with due date 12/31/9999 at the deferral level or is this standard SAP?

Valentina

0 Kudos

Hi Valentina,

To start with, Under which process are the due date of the Documents set to 12/31/9999?

Have you done any customization to set the Due date of certain document transactions to 12/31/9999.

Are you using any custom transaction to set the deferral date or you are setting it through FPE2/FPE2M.

So, if you don't want to set the deferral date for the transactions having due date as 12/31/9999, then you can do an enhancement in event 1106.

Check the sample FM, ISU_SAMPLE_1106 for more info.

Hope it helps..

Thanks,