Sir,

    In PS when I do Transfer and posting (412 Q) and Goods Issue (281 Q) for Inventory consumption, the goods are issued at the rate which appeared as MAP at time of first issue.

If More GR is done in inventory at some different price (i.e. MAP changes),additional GI to Project is done by old MAP only.It does not pick the then MAP.

I want that the goods get issued at MAP at that particular moment. Kindly guide for configuration/parameter

Accepted Solutions (0)

Answers (1)

Answers (1)

kenmelching
Active Contributor
0 Kudos

Are you using Plant or Project Stock?

If you are issuing from Project Stock (WBS) the moving average is specific to that WBS.  Look at table QBEW instead of MBEW.

So if you buy quantity 1 of a material and hold it in Project Stock the moving average is essentially actual cost.

0 Kudos

OK sir,

using 412 Q I create project stock and thn issue from this project stock to WBS using 281 Q.

I ll see tables.