Hi Andrea,
could you please post the long text of the error message? This would help to see if the issue is related to the system settings (which will most likely be the case).
I anyway would recommend to activate business functions directly within the respective target system and not via transport. For sure you should do it in the same sequence like a transport, i.e. first in DEV via QAS and finally in PRD in case all changes and tests have been successful.
Therefore you would temporarily need to "open" the system during the activation process. For PRD I would recommend doing this during a planned maintenance time slot.