Requirement not created at Manufacturing Plant

former_member343632
Participant
0 Kudos

Hi,

There is Manufacturing plant and DC.

T Lane exists between this two from Plant to DC.

There is demand sitting at DC and we run Heuristic at DC. This demand is not passing as requirement to Plant.

What could be the reason? Do I need to check some settings?

Regards,

Prabhat

Accepted Solutions (1)

Accepted Solutions (1)

rahul_agarwal5
Active Participant
0 Kudos

Hi,

Is this problem in Production ?

I would advise to replicate in a lower environment & check.

There may be various reasons for this.

Are you having the correct settings for Heuristics ?

Check if you have stock for same at DC already ?

kenneth_snyder
Active Contributor
0 Kudos

Which Heuristics.  SNP or PPDS?

Do you get any Stock Transfers for other materials/locations.

Did you try debugging before you ask for help?

former_member343632
Participant
0 Kudos

There was already stock.

Answers (0)