Planned order scheduled during downtime

Former Member
0 Kudos

Hi,

I've set downtime for maintenance in the resources in transaction PP/DS, and, the planned orders are scheduled to produce during downtime.

Currently I need to drag and drop each planned orders manually, which is very tedious to maintain if I've many planned orders during this period of time.

would like to ask if there's any other way to ensure no planned orders to be scheduled when downtime is set?

Regards,

Christine

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Christine,

When a downtime is created for a Resource, liveCache automatically reschedules the activities such that they will neither start nor end during the downtime, but this automatic reschedulling is not necessarily optimal.


Due to this, it is recommended to execute the Reschedule function or a DS heuristic for the Resource to adjust planning after creating downtimes .


Regards,

Tiago

Former Member
0 Kudos

Hi Tiago,

Is there any setting need to be adjust when execute the DS heuristic for the highlighted resources?

I've execute DS heuristic but the planned order is still scheduled on the downtime.

Regards,

Christine