on 05-04-2016 5:27 AM
Hi All ,
Please let me know if there is a way to copy projects/wbs elements from Production to lower lifecycles. It could be any method - BDC/LSMW/custom program/IDocs . .just give me a method..
Hello
What is the meaning of copy from Production & lower life cycles?
Is your project running in Production landscape?
You may explore BAPI_BUS2054_CREATE_MULTI and BAPI_PROJECT_MAINTAIN.
Shubham
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
By copying if you mean to replicate the entire project with transactional data , then the way out is to create the entire structure in quality / development.
You can create projects by using standard templates.
If its a cross client replication then you may have to take ABAP / BASIS support.
Shubham
Where are projects stored from SEGW ? | SCN
How to transport master data from production to... | SCN
Hello
There are some useful threads which you may go through.
What is the purpose of this replication is very important to understand?
Do you want to test something in Dev /Quality?
Shubham
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.