Hi

We are planning to utilize ACL in both PPM and PS spaces. Is there a way to copy the ACL from PPM Item into PS Project so there will be an alignment between the two spaces in terms of security. And similarly, once some authorized user updates the ACL in PS, is theer a way to update this in PPM Item level as well?

Regards

Savas

Accepted Solutions (1)

Accepted Solutions (1)

sammar81
Employee
Employee
0 Kudos

Hi Savas,

I don't think it is available in standard functionality. You may have to get it developed..As the objects for PPM and PS are different when it comes to ACL..

Regards

Sammar

S0022314014
Active Contributor
0 Kudos

Hi Sammar

We are actually looking for a BAdI or so which can handle this.

Regards

Savas

judith_gabriel
Contributor
0 Kudos

Dear Savas,

you can try to use BAdI INM_OF_SYNC.


Best regards,

Judith

S0022314014
Active Contributor
0 Kudos

Hi Judith

Many thanks for the input. It seems that will help. Correct me if I am wrong but this BADI can be used from PPM to PS information flow. How about therevrese: PS to PPM? 

Kind regards

Savas

judith_gabriel
Contributor
0 Kudos

Dear Savas,

the BAdI INM_OF_SYNC can be used to synchronize datas from PPM to PS.

One of the following BAdIs can be used to synchronize datas from PS-project to PPM:

BADI_CPPM_RPM_PS_SYNC_NET_ACT  (Network Activity Synchronization)

BADI_CPPM_RPM_PS_SYNC_PROJ        (Project Synchronization)

BADI_CPPM_RPM_PS_SYNC_WBS         (WBS Synchronization)

Best regards,

Judith