on 05-03-2016 12:30 AM
Hi Experts,
I have read and tested and have not found a way to plan on a higher level planning element and post on a lower level account assignment element and have EVM calculate (BCWS and BWCP). I have found that the POC's calculate yet the EVM does not.
Thank you,
Kevin
Hi Kevin,
I think for the BCWP etc calculations the planned cost should be at the desired WBS.. The formuals/Logic behind these calculations are confusing..
Let's wait for the experts to provide their insights on this..
Cheers
Samar