04-20-2016 1:41 PM
Dear Experts,
We have implemented GM,
The requirement is that the Purchase Order Commitment in the GM records, would be reduced once the Invoice is received.
Currently the PO commitment is reduced once the GR is posted, and not once the IV is posted (as we would like).
How can we change that?
Thank you
Orly
04-20-2016 3:26 PM
Hi,
What are your settings in OFUP? Does invoice create an update?
Regards,
Eli
05-02-2016 11:55 AM
Hi Eli,
Thank you for the answer,
I tried this - but it is for FM only,
Not changing anything in GM - I am looking for the same procedure in GM.
Regards
Orly