Planned order need to create 30 before forecast date

former_member309586
Participant
0 Kudos

Hi Gurus,

User wanted to have planned order created 30 days before the forecast date.

Can anyone suggest please?

Thanks in advance

Regards,

Rajesh Kumar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Rajesh,

You probably should investigate the concept of "Safety Time/act.cov" in the MRP2 tab of the Material master.  For more info, place your cursor on the field and press F1.

On the APO side, this will be integrated as "SZ" safety stock method, and the 30 days will appear as "Safety Days Supply".

Best Regards,

DB49