on 04-19-2016 9:20 PM
Hello,
That means there is no capacity available in that period non-working time. Check factory calendar assign to your resource also check if any downtime mainatined in resource master.
n the detailed scheduling planning board, working times are shown in white, regular non-working times (such as breaks and weekends) in gray, and downtimes (due to machine shutdowns, for example) in dark gray.
Refer useful SAP help document on it,
Scheduling in Non-Working Times - Detailed Scheduling Topics - SAP Library
Best Regards,
R.BRahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.