Hi,

We are using export functionality of cProject-MSProject. It is working fine.Now we are changing values in the MSProject and trying to update the existing project with the same. But, instead of updating the Project it is creating new cProject even though we have kept cProject number as file name. Also following below wiki we are not able to see this below highlighted option too.

cProjects (PPM) integration with MS Projects - Product Lifecycle Management - SCN Wiki

Are we missing anything in configuration?

Regards,

Alex

Accepted Solutions (1)

Accepted Solutions (1)

Shubham1
Employee
Employee
0 Kudos

Hello

Please refer to SAP note 1326709 and ensure that all steps are followed properly.

Regards

Shubham