Maintenance Order Dates different than operation dates

ali_dai
Contributor
0 Kudos

Hi all,

I have searched numerous threads for Basic start data and finish, but i have not find any solution to the following issue:

I have an order type with forward scheduling and in creation i give as start i,e 10.04.16 and finish 20.04.16.

However, the operation date takes as basic start and finish the current date and not the header dates.

I have gone through thread but no solution.

Can you please help me.

BR

Accepted Solutions (0)

Answers (7)

Answers (7)

ali_dai
Contributor
0 Kudos

Hi Paul,

Indeed in the scheduling it shows current date.

Actually with the below settings

i managed  to handle it.

but what only capacity means? what is the general impact?

BR

ali_dai
Contributor
0 Kudos

Hi all,

I believe it has something to do with the scheduling. Here are my screens:

Former Member
0 Kudos

In the "Dates" area on the order header screen, click the "Show further scheduling data" icon and post a screen shot of the full "Dates" data.

Paul

ali_dai
Contributor
0 Kudos

Hi Amol,

It is unchecked.... .

BR

former_member220863
Active Contributor
0 Kudos

Hi Ali,


" Default current date as Basic Date. This setting will not affect, you have to maintain Basic Start Date manually then.

In my system your scenario is working fine with below setting.

Not sure what you have missed. Please share your Header screen shot.

Regards,

Sunil

ali_dai
Contributor
0 Kudos

Here are my data';

header.jpg

I want automatically start of operation date to be the bsc. Start.

BR

former_member220863
Active Contributor
0 Kudos

Header Screen Shot??

Former Member
0 Kudos

Hi Ali,

I am not really sure but Could you please try by unchecking the " dafault current date as basic date for your particuar Plant in following customizing path.

PM-CS - Maintenance and Service Orders - General Data - Activate Default Value for Current Date as Basic Date.

Regards,

Amol

ali_dai
Contributor
0 Kudos

Hi,

I did by it did not work.

MTerence
Active Contributor
0 Kudos

Hi Ali,

Have you checked this setting in the work order, this can influence operation date.

Regards

Terence

former_member220863
Active Contributor
0 Kudos

Can you provide header and Operation Dates screen shot.

Regards,

Sunil

ali_dai
Contributor
0 Kudos

Hi,

The settings for my order type are:

Is it possible operation to take header start and finish date?

BR

MTerence
Active Contributor
0 Kudos

Hi Ali,

Use Adjust dates 1 and click Automatic scheduling

Regards

Terence

former_member220863
Active Contributor
0 Kudos

Please try below settings.

Regards,

Sunil

former_member220863
Active Contributor
0 Kudos

Hi Ali,

Operation dates will change once you define the work, also on the operating time of work center.

If your work center operation time is 8h, work define for operation as 10h then Operation Start Date will be today's date and Ende Date will be tomorrow's.

Regards,

Sunil

ali_dai
Contributor
0 Kudos

Hi Sunil,

I am setting as PM order start 10.04. Why in operation it takes 18.04 automatically? i do not have any scheduling in my work center. I do not have any capacity checks etc.

Thank you

MTerence
Active Contributor
0 Kudos

Hi Ali,

Double click the operation and click dates tab, share the screenshot

Check whether any Restriction like Start Point / End is set

Regards

Terence

former_member220863
Active Contributor
0 Kudos

Hi Ali,

Your operation dates will change to as per Basic Date once you save the order. Automatic Scheduling should be active in configuration for Plant and Order Type combination ( T code: OPU7). If not then manually schedule the order.

Regards,

Sunil