Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Bill of material issue

Dear Experts,

We have a situation during subcontracting , where the child part and head part ratio is 1:1 in bill of material   , But during goods receipt  there is wrong depletion of child part ,say for 1000 head part  numbers , there is 1230 Child parts.

I kindly request to provide me the solution for this problem.

Regards,

Mridula

Former Member
replied

ok this screenshot shows that there was no subsequent adjustment. Still it is not known if there were changes to the BOM

Your second component quantity is as well not linear proportional to the receipt quantity

2 View this answer in context
Not what you were looking for? View more on this topic or Ask a question