CJ30 Budget based on only Cost Plan Values

Hi All,

My client wants to do CJ30 only by copying the Plan Values and not direct input of budget amount.

Can we achieve in standard?

Regards,'

Suman

replied

You can create a custom role and put CJ30 budget values only in display mode.

Assign relevant user IDs this role. Its a simple way to utilize roles and authorizations in PS

Your Basis consultant can help you in this.

Shubham