CJ30 Budget based on only Cost Plan Values

former_member299514
Participant
0 Kudos

Hi All,

My client wants to do CJ30 only by copying the Plan Values and not direct input of budget amount.

Can we achieve in standard?

Regards,'

Suman

Accepted Solutions (1)

Accepted Solutions (1)

former_member299514
Participant
0 Kudos

Hi,

Yes know about this.

I want to restrict to use this method only. User cannot directly go and put a budget amount.

He can only have to copy.

Regards,

Suman

Shubham1
Employee
Employee
0 Kudos

You can create a custom role and put CJ30 budget values only in display mode.

Assign relevant user IDs this role. Its a simple way to utilize roles and authorizations in PS

Your Basis consultant can help you in this.

Shubham

Answers (2)

Answers (2)

Shubham1
Employee
Employee
0 Kudos

Alternate option is T code IMCCP3  - Transfer planning cost of CJ40 to CJ30.

Shubham

Shubham1
Employee
Employee
0 Kudos

hello

This is very much a standard practice in SAP PS.

Please follow below steps  :

  1. You can copy the cost plan of CJ40 in to budget CJ30
  2. Go to CJ30 & open your project
  3. Select all WBS  : Edit ->click on copy view -> select planned total
  4. Maintain % if required.

This will copy the cost plan value in budget.

Regards

Shubham