on 04-26-2007 2:05 PM
hi
am sanded a one quest dev to prd . am imported that request in prd.
it is possible to take back import request .
is there any way take back request.
when am imported request that time one program changed .now want to take a old position of that program.
Hello Mahesh,
Well though you cannot take back the request what you can do in this case is retrieve the old version of the program in your development system using version management in SE38 and then activate this old version. Save it in a transport and move this transport to your production. This will bring the status of the program to the old status.
In development go to SE38 (if this a report). Then give the report name and go in change mode. From menu bar select utilities---versionsversion management.
Then select the older version and use retrieve option in application tool bar.
Please award points if it helped.
Regards.
Ruchit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.