on 04-14-2016 3:17 AM
Dear all,
In my IDES SCM 7.0 EPH1, I try to create fixed pegging relationship:
1: Product Master:
2: In productView:
there is sufficient stock, and serveral DepDmd & OrdRes, also, I can create fixpegQty in pegging overview manually.
Now I like to setup job run on /sapapo/CDPSB0.
or my own heurstic ID which copied from SAP_PP_019 with user-define:
Problem: after Production planning Run, in log: MRP is ok with result, but step2, without log record, is NOT result, not error showing so strange, in my company, this function is working well.
could anyone help on it, thanks.
Best regards, Allen
Hello,
Did you set the indicator Display Log in /SAPAPO/CDPSB0?
Also check corresponding planning log in T-code /SAPAPO/RRPLOG1.
In SPRO:
> Advanced Planning and Optimization
> Supply Chain Planning
> Production Planning and Detailed Scheduling (PP/DS)
> Application Logs for PP/DS
> Maintain Exception Groups
You can define the messages.
Check Customizing transaction /SAPAPO/RRPCUST1 Only errors, terminations and warnings' in the global Customizing is set.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.