Hello Experts,

We have a requirement where we would like to trigger change output on purchase order when PO confirmation posts via ORDRSP, when we add confirmation manually system triggers the output successfully but when we post idoc ORDRSP system doesn't recognize the change and doesn't trigger the output, however I see change on the PO.

How can we achieve this requirement? is there any standard config? or do we need to put any custom logic?

Thanks

Jay

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor
0 Kudos

Couldn't this actually lead to an endless loop between the 2 systems?

Former Member
0 Kudos

Actually we would like to send the output to third party system so PO status in that system will advance to "Accepted". If solution will be a custom approach then we can try to invoke the output relevant to third party system only.

JL23
Active Contributor
Former Member
0 Kudos

Thanks Jurgen for your suggestion.

We have implemented the note, however we still don't see output is getting triggered. We have opened an OSS message with SAP.

Jay