Weekly Forecast in MD63 , Requirement Date in MD04

Hi,

Currently the forecast in MD63 is uploaded either in weeks(W) or months(M). And when I look at MD04, I can see that requirement date for that particular VSF is coming by default as 1st date of the week or 1st date of the month based on how forecast is entered in MD63 (whether in W or in M)

Where is the setting that by default it takes 1st day of the week\month as the requirement date. My requirement is to have last day of the week and last day of the month as requirement date.

Regards

Former Member