Capacity Levelling at activity level

Hi All,

I want to check capacity of my internal activity for which I have assigned workcentre on that activity.Formula which I'm using capacity is 'SAP008' After assign hours to activity, when I run 'CM05' report for Overload and 'CM01' for Load, I'm not getting desired result as I have assigned assign many hours beyond available hours.

Below is the screen shot of workcentre and others:

For capacity check on network:

Hour assigned on activity

After scheduling when I run 'CM05' capacity overload, I got this error message

I have also run 'CM01' Capacity Load report so it's showing me only operating hours.

So kindly guide me where I'm missing to get desire result.

Regards,

Faizan