on 04-13-2016 9:10 AM
Hi All,
I want to check capacity of my internal activity for which I have assigned workcentre on that activity.Formula which I'm using capacity is 'SAP008' After assign hours to activity, when I run 'CM05' report for Overload and 'CM01' for Load, I'm not getting desired result as I have assigned assign many hours beyond available hours.
Below is the screen shot of workcentre and others:
For capacity check on network:
Hour assigned on activity
After scheduling when I run 'CM05' capacity overload, I got this error message
I have also run 'CM01' Capacity Load report so it's showing me only operating hours.
So kindly guide me where I'm missing to get desire result.
Regards,
Faizan
Hi All,
Can anyone answer my question?
Regards,
Faizan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Few check points from my side
Do let us know the status of issue.
Shubham
Hi Shubham,
I have check points which you have highlighted:
So after doing that, still I'm not able to view result in 'CM05' report.
Regards,
Faizan
Hi Faizan,
Can you please check at the network header level for these activities if capacity planning is checked or not?
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.