S094 info structure not updated with MTO receipt element details (purchase.req)

Former Member

Hi,

I am trying to update S094 info structure after MRP run, and I am updating through report RMCBDISP.

This works well for MRP strategy 40, but when I use strategy 20 and run MRP the stock/requirement details are not getting updated in S094.

Any idea?, Please share your thoughts.

Thanks,

Ramu

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor

Hello,

You can fill S094 / S194, only the planning segments "Gross requirements planning" and "Net requirements planning" are taken into account in the standard system. However, further planning segments can be taken into account if required. For more information, see SAP consulting note   1271320 - S094/S194: Instructions for admitting new planning segments

Best Regards,

R.Brahmankar

Former Member
0 Kudos

Thanks Brahmankar,

This note looks promising, I will try to implement the note and confirm you.

Former Member
0 Kudos

Thanks Brahmankar,

I checked the note and added the logic in the implicit enhancement, this worked successfully.

Thanks you for input.

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please close the discussion, if your issue is solved.

Best Regards,

R.Brahmankar