on 04-11-2016 7:40 PM
Dear Experts,
Need quick help on types of consistency checks for Demand Planning.
By point wise, need help in knowing types of consistency checks required for following activities.
1 . Type of consistency check required before and after planning area initialization every month.
2. Type of consistency check before and after cvc creations automatically (frequency- monthly once ) and manually when required cvc
3. Type of consistency check before releasing forecast to SNP.
4. Type of consistency check before taking backup of monthlyplanning to cube for KPI.
TIA
Hi
Please find the answers to your different questions.
1 . Type of consistency check required before and after planning area initialization every month.
/sapapo/ts_pstru_cons_check
/sapapo/ts_lcm_plob_delta_sync
/SAPAPO/TS_LCM_CONS_CHECK
2. Type of consistency check before and after cvc creations automatically (frequency- monthly once ) and manually when required cvc
/sapapo/ts_lcm_plob_delta_sync
/SAPAPO/TS_LCM_CONS_CHECK
3. Type of consistency check before releasing forecast to SNP.
/SAPAPO/TS_LCM_CONS_CHECK with check SNP Master Data option clicked.
4. Type of consistency check before taking backup of monthlyplanning to cube for KPI.
/sapapo/ts_lcm_plob_delta_sync
/SAPAPO/TS_LCM_CONS_CHECK
/SAPAPO/TS_PAREA_EXTR_DS_CHECK
Please do let us know if this information helps you.
Thanks
Amol
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.