on 04-11-2016 4:19 PM
Can Anyone help me in Factory calendar in SAP, I want to change one Factory Calendar ID (extend the date) is there any impact will happend on the other ID or system?
Dear Amol,
Extending period will not have any Impact but
%% Factory calendar customization is cross client so make sure that existing settings of other factory calendars used by other plants are not getting disturbed. %%
If your system uses multiple plant and FCAL,it is advisable to extend the period in PROD system itself.
Regards,
Velmurugan S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It is advised to move the factory calendar change transports only one the week ends. The reason is the transport does not move the change only to a specific plant. You would move the whole set calendars for all the plants.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It is advised to move the factory calendar change transport only on the week ends.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
If you only want to extend the calendar validity, I don't see any negative impact.
Regards
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.