source of supply determination


Hi guys,

I get a problem when I create SNP planned order manually in planning book. The product has fixed lot size. If I input the quantity which is just equal to the fixed lot size system can pop up source of supply determination window and ask me to choose one of the PDS. Then I will get a new SNP planned order with PDS data. But if I input the quantity is multiple of the fixed lot size system doesn't pop up source of supply window. So the new SNP planned orders are without the PDS data. Does anybody know this is a standard behavior or this is an error?

Thanks.