Change Supplier - Business Activity .

Former Member
0 Kudos

Hello,

For some reason I don't know when I try to change my supplier I get the following error ,

  I have created a change request for change and assign the business activity ( SUP2 ) but still get the error , what I am missing  ?

Also I dont see the changing button in the following menu , maybe is because is for the same reason.

Thank you.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Jose,

It is due to missing Business activity in the Change Request Type of Process Supplier.

Please check Process Modelling -> Create Change Request Type and maintain the Business activity as below

Former Member
0 Kudos

thanks , It is exactly what I did.

Former Member
0 Kudos

Hi Jose

Issue got solved? If not which role you are using ? Standard or custom role ?

Former Member
0 Kudos

Hello MDG User ,

Well , I am still trying to figure out whats going on  , I have used business activity VPL2 instead of SUP2 and it works. However I woul like to know why , I have check the deifinition of both BA and they are the same...

former_member209780
Active Participant
0 Kudos

Hi Jose,

Reason could be that you don't have authorizations to that change request type or the change request type is not setup properly. Please check the authorizations and if that is not the issue please post some screenshots of the CR type created.

Thanks