Target cost not calculating in some production orders

Former Member
0 Kudos

Hi all,

we have some production orders in which the target cost is calculating properly and in some production orders target cost is not calculating.

I have checked two orders both the orders have used same kind of material for production and every thing is same but in one order target cost is calculating and in another not.

Both the orders have status REL DLV.

Pls help.

thanks in advance

Accepted Solutions (0)

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

The target cost calculation requires a cost estimate for which the cost component split is active in company as well as in controlling area currency.

The cost component split in controlling area currency is not active for the costing variant (check T-code: OKKN or OKY9).

Therefore the variance calculation issues message KV169 and cannot calculate target costs.

Message KV151 'Only total variance in version & because of missing target

You need to activate the cost component split in controlling area currency in the setting of costing variant. Then the newly created cost estimate will have the correct data. For newly created order, the target cost will be correctly calculated.

For existing orders (with old setting), you can consider to implement SAP Note 1229004 get rid of the problem.

Also Refer consulting note 151579 - Variance calculation: incorrect target cost version 0

Best Regards,

R.Brahmankar

Former Member
0 Kudos

hi,

if  there is any problem like this then why it is calculating the target cost in other production order of same material

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

You should consult to your CO consultant on it.

You should have valid cost estimate for the material  on current date.

Best Regards,

R.Brahmankar

Former Member
0 Kudos

But on both the production order we are using same material and one order is calculating target cost and another one not. If there is any configuration or setting problem the error should occur in both the orders but it is not happening.

former_member198692
Active Contributor
0 Kudos

Hi ,

Sorry for interruption but let me know

In which period order is created which show target cost ?

Regards

Prasad

Former Member
0 Kudos

same this year both the orders were confirmed this year means april 2016

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Check OKTZ whether Cost Component Structure is activated or not

Also both the production order are make to stock and for same product.

Check if the material has a standard cost updated through standard cost run. The target cost is based on the standard cost estimate.

Check if there was a valid standard cost estimate at the time of the creation of the order.


Best Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

Yes Cost Component Structure is activated and we are using make to order scenerio and in material master standard cost is maintained.

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Is it valuated sales order stock with standard cost estimate?

Did you check if there was a valid standard cost estimate at the time of the creation of the order?


Best Regards,

R.Brahmankar

former_member198692
Active Contributor
0 Kudos

Hi,

Check you calculate variance for your order where you are not getting target cost.First run KKS2 for your order then check target cost is calculated or not.

Also see the status should be VCAL if variance is calculated

Check below link for your reference

Regards

Prasad

Former Member
0 Kudos

hi,

I have already run this tcode KKS2 and it is giving me error Only remaining var. in version 0 - no target costs for 000000239341

warning msg No standard cost estimate for material 80000010 in plant VW01 on 07.04.2016

and information msg One order (item) processed.

I have created another order of same material inwhich the order cost is getting calculated.

regards

former_member198692
Active Contributor
0 Kudos

Hi

For this month Std cost estimate is taken or not?

If not then you can not get variance and target cost either.

Check below link

Only Remaining var. in version 0 - no target co... | SCN

The order which show target cost is created on which month?

Regards

Prasad

Former Member
0 Kudos

hi,

if  there is any problem like this then why it is calculating the target cost in other production order of same material.