Production activity cannot be transferred during the PPM CIF

renato_parise
Participant
0 Kudos

Hi,

We have some production activity that cannot be transferred during the PPM CIF.

When I check the routing, the operation (Base qty) has 7.043 pieces per hour. (I think less then 0,000 hour in PPM).

That is the real problem? How can I fix it?

Thanks,

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

In this case use the activity unit of measure as minutes (MIN)  then you will have time duration to CIF.

you can change the base unit of measurement of the capacity category relevant to scheduling, for example, from hours to minutes - in this case, the calculated duration is transferred in the unit minutes, that is, the value becomes bigger.

Refer consutling note    448085 - PPM transfer: Tips and tricks

The operation without times can be send to APO if parameter FLG_TRANSFER = 'X' in user exit FUNCTION EXIT_SAPLPGS1_002 -> Include ZXPGSEU02.

Best Regards,

R.Brahmankar

renato_parise
Participant
0 Kudos

Hi Brahmankar.

Thank you for your quickly answer.

I will try to change the base unit of measurement of the capacity category and probably I will use this User Exit.

Thanks.

Parise.