Integration of SD Schedule Agreements from an R/3 4.6c ERP system

former_member311174
Discoverer
0 Kudos

Good morning,

I am currently looking at integrating a 4.6c ERP system to SCM7.

When looking to integrate Sales Schedule Agreements via creating an Integration Model in CFM1, I can not see any obvious selection.

I have done the above for the same SCM7 system with an ECC6 system and it is clear that this is defined as an option in CFM1.

Am I missing something, I thought it may have come under the Sales Orders selection but the help text does not specify.

Thanks in advance,

Guy.

Accepted Solutions (1)

Accepted Solutions (1)

former_member311174
Discoverer
0 Kudos

Hi thanks for the response, this selection is purely for Purchasing Scheduling Agreements

kenneth_snyder
Active Contributor
0 Kudos

sales order scheduling agreements should CIF over with normal sales orders.  Is it not working?

former_member311174
Discoverer
0 Kudos

Hi Kenneth, thanks you were right

It has been a while since I have worked in a 4.6c environment.

It is interesting to see such a difference into how they are represented in APO as with an ECC environment they are represented as a Master Data object.

They joys of integrating multiple ERP systems to APO

Answers (1)

Answers (1)

rvarulselvan
Advisor
Advisor
0 Kudos

Create integration model in cfm1..then activate in cfm2

former_member311174
Discoverer
0 Kudos

Hi, thanks for the response, yes I am aware of the above for the ECC releases but I am trying to find a solution for R/3 4.6c:

rvarulselvan
Advisor
Advisor
0 Kudos

try under material dependent objects....

scheduling agreements