Hi Everyone,

Please help me with this issue:

A material "X" with mrp type E1(Order on Demand). Is having stock 0, a PO was created for 1 quantity and it appeared on MD04 screen. Later when we run the mrp run for that PLANT. That X material created a Planned Order and that is appearing on MD04 screen.

Please advice me why material X created a planned order even though there is one PO in MD04 screen?

Former Member
Former Member replied

Hi Sailaja,

Is that PO is in on Order Stock or Stock received. If Stock recieved it won't create the Planned order but if it is in On-order it will create.

Regards,
Raghu Raj