on 04-05-2016 10:21 AM
Hello,
With PPM, it is possible to Roll-Up costs from PS project to Item and then to Initiative and Buckets.
Is it possible to do the same frome PPM Project to Item: I am doing costing within a PPM project (via Role costing) and i am looking to agregate this cost planning in the Item level.
Possible ?
Many thanks
Hello
Yes it is...
Take a look at the standard setup required under : Base System Interfaces -> Define Financial Planning Settings. Then on the left the option for mapping "...Financial Views to Proj. Mgmt Role Function"
Regards
C