on 04-05-2016 12:05 AM
Dear friends
I am confused by the MRP indicator in SOURCE LIST.
I have two vendors A, B.
in Source list, I set both of them are not relevant to MRP , as "blank"
and I create a quota arrangement as well for both vendors.
.
in such a scenario, when I run MRP, the system still created PR orders automatically for both vendors, split the quantity between them.
I am confused , since in SOURCE LIST, both vendors are not relevant to MRP.
why does MRP still created PR order for those vendors?
Thanks.
Tang.
Hi,
While assigning the source in MRP, the quota arrangement has the highest priority and hence the source is assigned even though its not relevant in source list.
Refer the wiki: Source Determination within ECC system in Purchasing - ERP SCM - SCN Wiki
- section: MRP – Automatic source assigning
Regards,
AKPT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
got it , thank you , friends.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Refer SAP note: 1224603 source list integration incomplete.
Regards,
Biju K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.