Dear all,

I have created the special rule in factory calendar for the month of June 11th to 30th as holidays.

But when i am running the MRP the system is generating the requirements on this mentioned days.

How to restrict this my requirements is system should throw error message telling that its a holidays.

IS there any possibilities kindly guide me.

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member328966
Participant
0 Kudos

Hi ,

thanks for your support.

Closing this issue

suresh_bachan
Active Participant
0 Kudos

Hi Vishnu,

Your special rule assignment seems to be correct. Please check the following 2 parameters.

1) your calendar at plant level (OP03), Is this also EE?

2) your calendar at work center level for inhouse productions

Kind regards

former_member189817
Active Contributor
0 Kudos

Hello Vishnu ram,

Can you please share the screen shot of FCAL and MD05

Regards,

Velmurugan S

former_member328966
Participant
0 Kudos

Hi Velmurugan ,

Kindly check for the attached sheet.