Hello,
What is the best way to setup a conditional Tolerance Limit in Internal Order budget with the following logic:
1. Absolute Variance of $1,500 if 10% of Budget is less than $1,500
2. Otherwise, maximum variance is 10%
Thanks.
Hi John
This is not possible in standard Sap. What I feel is eventually every budget will fall below 1500 at some point in time. So what matters is only Rule 1
rule 1 can be set up in Sap
Ajay M