Assembly Processing: Message Create network: Project Allocation

Former Member
0 Kudos

Hi Experts,

We have an issue here where have been using Assembly processing. Now we are extending the process to new company code.

CN09 has been maintained

But when saving the quote we get this error message

The material being used is mapped to Std project 53100059 , but not sure why its showing the below screen and two Std ProjDef.

When I try to cancel it gives another message " Enter a CO Area, company code, or plant"

and then it gives message "error when processing network" and kicks out of the document.

Appreciate if you have any suggestions.

Regards,

Krishna

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI Krishna,

Check whether you have same WBS in standard network and in CN08. If they differ there are chance of getting such message.

Regards,

Pradeep

Former Member
0 Kudos

Hi Pradeep,

I checked and it was correct.

But that helped me to revisit the std network were I saw that the some of the WBS were mapped to a different WBS.

Thanks

Krishna