Hi,

I noticed the responsible cost center and requesting cost centers are greyed out when i create the WBS element for a particular controlling area. If i create the WBS element using the same project profile BUT a different controlling area, both fields are available for input. Does anyone know what is the issue here?

Accepted Solutions (1)

Accepted Solutions (1)

former_member218047
Participant
0 Kudos

Hi Sanjay,

Kindly check the field selection for WBS and opt for input/Required for the said fields. And also check the influencing settings for controlling area and change to required controlling area.

Regards,

Seshagiri

sanjay_ram
Participant
0 Kudos

Thank you sir.

Answers (1)

Answers (1)

MTerence
Active Contributor
0 Kudos

Hi Sanjay,

Check OPUK

Regards

Terence

sanjay_ram
Participant
0 Kudos

Awesome, that explains, may i know the menu path for this as well?

former_member218047
Participant
0 Kudos

SPRO--PS--Operative stru--WBS--User interface settings--field selection for WBS.