Hi Experts,
we are using overall budgeting with availability control activated to 80% and 100% in Overall as well as Released Budget and creating commitments through ME51N , Issue is every time we update the original budget CJ30 we are required to run CJBN and CJEN , i tried with Supplement Budgeting also but that too populates the same error of "Budget Exceeding" even though it has sufficient budget.
Please suggest.
Regards
Abhishek Singh
Hi,
2257155 - KO30/CJBV do not activate availability control.
2263077 - Missing or unjustified messages for availability control for releases.
with these notes we have resolved the issue .
Regards
Abhishek singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Abhishek
Confirm that you have not done any change in the Budget profile after the project was created
another point is you might have activated the availability control after some cost was captured over to the project.
in this scenario it is advisable that you revoke the entire budgeting status and then again budget it and activate AVAC.i am sure it shall work in this case. try it in ides client prior to change in development
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This should not come always, check for possible SAP notes, i got below note, which looks like a collection of multiple issues, check it.
1532931 - Budget Overrun/ Exceeded
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Terence,
Thanks for your reply i have already gone through that Note and that has worked too but my problem is every time when i update the original Budget i need to process all the steps again or sometimes it worked after running CJEN and CJBN .
Is it normal that when ever you are changing the Original budget you are required to run these steps?
Regards
Abhishek singh
Hi,
No, that's not a standard behavior.
If you update in CJ30 to 1000 and then in CJ20n if it exceeds 1000, it will trigger an message.
Is AVAC is active for your WBS element ?
Additionally refer to below note
1245966 - Activating the availability control for activation type 1
Regards
Terence
Hi,
Normally, this should not occur. So we need to understand whether some thing is stopping the update.
Check whether this issue occurs for all projects, also check whether there is any process or custom program needs to be done, since they might have stopped the automatic budget calculation.
In case if you are able to replicate the scenario, raise a OSS note to SAP for fixing it.
Regards
Terence
Hi,
Thanks for the update. Share us what resolution SAP provides. Have you checked below note
1606591 - Unjustified error messages when entering budgets or releases
Regards
Terence
Hi Abhishek,
Please implement note 166394 and try it. Hope it resolves your issue.
Regards,
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.