Requirement Grouping - Budget Process

former_member225123
Participant
0 Kudos

Dear Experts,

Need your inputs on below points.

Our client is wishing to use requirement grouping,

1. Create Project structure with all WBS and Activities.

1.1 Maintain Grouping indicator (2 - Grouping for selected MRP groups)

1.2 Assign MRP group with Project and plant.

1.2 MRP run (on Grouping WBS)

1.3 PR's created on Grouping WBS and Receive stock on grouping wbs.

1.4 Issue based on Reservations created on individual wbs elements.

Here, It is required to maintain budget at Grouping WBS as well as individual WBS's. Budget at Grouping WBS for taking inventory in Grouping WBS and at indidual wbs for issue stock based on there material requirements. Client is not happy to maintain Budget at both levels. Although after distribution of requirement to individual wbs would Credit the budget at Grouping WBS  Is it possible for system not to check Budget on individual wbs element ( Grouping WBS ).

I have implemented this process first time. Also suggest if you can foresee any issues in this process.

Regards

Gaurav Ahuja

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member225123
Participant
0 Kudos

Hi paulo,

I created user status to block Availability Control on Individual Indicator which also not working.

Can u please suggest which Business Transaction would have to Forbid. I choose Availability Control and Forbid.

Regards

Gaurav Ahuja

MTerence
Active Contributor
0 Kudos

Hi Gaurav,

Refer this thread. Its possible via User Status

Availability control disappear in OK02 object type | SCN

Regards

Terence

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Gaurav,

You can block availability control on individual WBS using a user status.

Regards,

Paulo

former_member225123
Participant
0 Kudos

Hi Paulo,

Thanks for reply.

I haven't set user status to block availability control before. Let me check this.

Could you please suggest is it a right process to create separate Project / WBS's for grouping of requirement, Here Availability control will not activate as long as budget not maintained and release.

Also, please suggest what kind of issues come in Grouping Process.

Appreciate if you can suggest how automatic requirement grouping is different from Grouping maintained at WBS elements ( use of GRM4 , GRM5, GRM2 ).

Industry is construction. what would be better solution.

Regards

Gaurav Ahuja