on 03-17-2016 8:17 AM
Dear Experts,
Using easy cost planning I have created planned values in IMA11 I want to copy same values to the project budget in IM52.
In im52 I can see only manually budget assigned to the project. I want to copy the planned line item as budget.
How should I do this please help me on this
Regards
Praveen
Hi Praveen,
You can copy AR planning into measure planning automatically, but not directly into the budget. That is additional manual step in the standard system to copy from plan to budget.
If you want to automate the process it will be an enhancement.
Regards,
Paulo