Dear friends, we have a Business Suite System on HANA (ERP 6.0 EHP 7) and we have in a separated server de  PAS (Primary application server).Due to some requeriments, we have to move de HANA Database server to other host (Different hostname and HANA SID). We have planning to take a backup of the original HANA system, and then restore on the new HANA server, then, modify all the profile parameters of the DEFAULT and instance profiles pointing to the new Server and new SID, aditionally, we going to modify the HDBUSERSTORE with the data of the new server.

From our perspective, this procedure  would be working. But if you think that we passed something, you help will be appreciated.

Thanks and best regards.

Hector Ganga.

Accepted Solutions (0)

Answers (1)

Answers (1)

nicholas_chang
Active Contributor
0 Kudos

Hi Hector,

Yes, it will works.

You can just test it out on sandbox, dev before do it on prod.