on 03-11-2016 3:33 PM
Hi,
We are working on a planning area which is a copy of SAP2. We have generated Consensus demand plan. We are able to populate Customer Sourcing Ratio for each time period in Prod-Loc-Cust planning view.
However we are unable to populate the dependent demand quantity at the DC which is a sourcing location for the customers. We ran the "Unconstrained Demand and Supply (No Shortage)" and tried to populate the values of dependent demand quantity. However we did not succeed. Not sure where we are going wrong. Please help.
Regards
Atri Kundu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.