CJ40 and CJI9 are not matching

Former Member
0 Kudos

Dear All,

I have planned five WBS by CJ40 in different currencies but one of the WBS plan value is not coming in CJI9. 

I have checked table RPSCO against plan value  and table entries are matching with the cost plan done but not matching with CJI9.


Why this is happening with CJI9 ?? What to be done .


Awaiting for your respond.


Thanks Advance.

Accepted Solutions (1)

Accepted Solutions (1)

sunil_yadav2
Active Contributor
0 Kudos

HI Ankit,

if this issue is coming for only one WBS than their might be some differences in these WBS.

Try CJEN and reconstructing the project info database.

please go through below links also:

Project planned value reports | SCN

thanks

Sunil

Former Member
0 Kudos

Hi Sunil,

Thanks for the respond.

I have already done CJEN and CJBN also. This issue is happening with many 5-6 WBS from different projects.

Please suggest something.!

MTerence
Active Contributor
0 Kudos

Hi Ankit,

Not sure, whether this is the issue.

When you execute CJI9, have you checked Overall values or not ? Just check it and execute

Rergards

Terence

Answers (1)

Answers (1)

kenmelching
Active Contributor
0 Kudos

Values entered in CJ40 do not write plan line items (COEP), CJ40 only writes the plan values to the summary table (COSP).

Former Member
0 Kudos



Thanks Ken for your kind respond.


I have planned five WBS by CJ40 in different currencies but one of the WBS plan value is not coming in CJI9.


Please suggest ??

Former Member
0 Kudos

Dear All,

Please any body respond on this.

Thanks Indeed.