Dear All,
I have planned five WBS by CJ40 in different currencies but one of the WBS plan value is not coming in CJI9.
I have checked table RPSCO against plan value and table entries are matching with the cost plan done but not matching with CJI9.
Why this is happening with CJI9 ?? What to be done .
Awaiting for your respond.
Thanks Advance.
HI Ankit,
if this issue is coming for only one WBS than their might be some differences in these WBS.
Try CJEN and reconstructing the project info database.
please go through below links also:
Project planned value reports | SCN
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Values entered in CJ40 do not write plan line items (COEP), CJ40 only writes the plan values to the summary table (COSP).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.