Hi all,

I have successfully rejected ID and it is in completed status.

Whereas in IDN almost all activities are completed except DVE Version is active.

Do we need to reject IDN as well ?

Regards,

Sunil

Accepted Solutions (1)

Accepted Solutions (1)

Ajit_Routray
Active Contributor
0 Kudos

Hi Sunil

DVE Status in IDN   =Active(A) means ID created

                               =Inactive( D) means ID not created

Once DVE Status is activated in IDN, we can not reject from IDN , for reject , we have to use rejection in ID.

Impact of Rejection: Quantity will be zero ,status changes and also updated to Source system( ECC ) through PPF.

Do we need to reject IDN as well ?

No Need if you already rejected the ID.


Also check ID in ECC that the quantity gets updated or not .


Let us know if you have further queries.

Thanks

AR

Former Member
0 Kudos

Hi Ajit,

So there is no need to reject IDN once ID gets rejected ?

Status overview for ID in ecc has updated to C .

Can we delete the Inbound delivery document in ecc .

Regards,

Sunil

Ajit_Routray
Active Contributor
0 Kudos

Hi Sunil,

So there is no need to reject IDN once ID gets rejected ?

not require, even if you try to reject IDN , you cant because version is already activate.as I explained in my earlier post.


Can we delete the Inbound delivery document in ecc .


We cant delete If It is already distributed.



Thanks


AR





Former Member
0 Kudos

Hello Sunil,

Once you successfully reject the ID ,document is completed in EWM .

At same time EWM system will trigger PPF action to communicate ECC system.

Hence you can close the ID in ECC system if you wish to do so.

BR,

Olet

Former Member
0 Kudos

Thank you all .

Regards,

Sunil