Low level code determination issue

0 Kudos

Dear Experts,

I have an issue with the SAP_PP_020 heuristic. The problem is that the LLC is not calculated for the components that are externally procured.

The components are included in a PDS for the FG. They do not have a source of supply (the info record is not CIF-ed at the moment).

The SAP_PP_020 heuristic is returning the following message: "No supply sources were found for the model 000".

My question is: Is it necessary to have a source of supply for the component? What workaround do you propose?

Thank you in advance,

Hrvoje

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hi Hrvoje,

It's not necessary to have a source of supply for the component, but the finished product which has the PDS consuming the externally procured component should be included in the selection of the Stage-Numbering Algorithm.

If the externally procured components do not have a source (TLane), make sure note below is implemented in the system:

2048721 - SAP_PP_020: Stage-Numbering Algorithm heuristic does not calculate the low level code for products without a source of supply

Regards,
Tiago

Answers (2)

Answers (2)

jyotichalikar
Participant
0 Kudos

Hi Hrvoje,

Source of supply is not required for components.

You need to run MRP heuristic "SAP_MRP_001" along with stage numbering algorithm to generate low level codes.

Thanks & Regards,

Jyoti

Former Member
0 Kudos

Hrvoje,

Check your settings in /SAPAPO/MVM.

Best Regards,