on 03-08-2016 12:21 AM
Hi,
I need to extract the information of all the WBSs which were used during 2014 and 2015 for T&E with the following information.
Could you please help me to know from which table can I extract the information? I looked fro PRPS and PROJ tables but I couldn't get it.
Type | Description | Structure | Used in 2014 or 2015 | GL account range | Comment |
---|---|---|---|---|---|
WBS | CAPEX | C-XXXX/XXX/XXX | 1000 | 81301840 for Capital | Example |
8130xxxx for rest |
Thanks and regards!
Hi Maria,
You can approach this either from PS side or from the FI-TV side (tables).
Hopefully you have a designated document type for things posted from FI-TV, therefore you can take a line items report CJI3 with a filter for that document type.
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
In PTRV_SCOS-WBS_ELEMT you will get the WBS affected to an expense report.
You can then search all trips for a given period with this field filled.
Regards,
Christophe.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.