Dear All,

I have done overall cost plan in version 0 through t code CJ40 in USD.  When i am trying to copy this through IMCCP3 (version 0 and project) then system is showing data copied successfully and AVAC also activated automatically but if i am executing CJ31 there is no value coming up.

1. Why budget is not getting copied ?

2. Can plan cost in multiple currency (USD )also can be copied in same way to budget in USD.  ?

Please Suggest.

Thanks in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

1. Check if note # 2002148 is applicable. 2. Copy program can write values in all currencies (also depends on budget/plan profile currency parameters)