Recently i have run SGEN on our DEV server.logs show everything fine but in st22 it show GEN_FRAGVIEW_EMPTY dump

Date    Time  Message

04.03.2016  13:47:28  Job started

04.03.2016  13:47:28  Step 001 started (program RSPARAGENER8, variant &0000000000001, user ID abcd

04.03.2016  13:47:28  Task: Generate all objects of selected software components

04.03.2016  13:47:28  Data basis: all_components

04.03.2016  13:47:28  Control program of the parallel processing on host dqserver was started

04.03.2016  13:47:28  Server dqserver_DSR_00 is used during parallel processing

04.03.2016  13:47:28  Generation for machine type   562

04.03.2016  13:47:29  7 parallel jobs have been scheduled to generate 198,033 objects

04.03.2016  13:47:29  Each job processes 400 objects for one run

04.03.2016  18:33:55  Task   7 completed

04.03.2016  18:34:34  Task   5 completed

04.03.2016  18:34:47  Task   1 completed

04.03.2016  18:34:52  Task   6 completed

04.03.2016  18:35:11  Task   2 completed

04.03.2016  18:35:24  Task   4 completed

04.03.2016  18:36:24  Task   3 completed

04.03.2016  18:36:25  Detailed information on parallel processing -> Spool -> Display contents

04.03.2016  18:36:25  Job finished

Accepted Solutions (1)

Accepted Solutions (1)

Sriram2009
Active Contributor
0 Kudos

Hi Singh.

1.  Could you share the ST22 dump as attachment? share the SAP version details?

2.


04.03.2016  18:36:25  Detailed information on parallel processing -> Spool -> Display contents

Could you check the Spool if possible share the snapshot

Regards

SS

Former Member
0 Kudos

we are using ECC6.0 on windows 2003 server

04.03.2016Parallel Processing of the Generation of ABAP Loads     1

SAP Load Generator - Transaction SGEN  Rel. 700 / SPL 0015

user: JCTALL   system: DSRgeneration task:   1

Parallel processing

Started Task:1  at  13:47:29 processing 400  objects
Started Task:2  at  13:47:29 processing 400  objects
Started Task:3  at  13:47:29 processing 400  objects
Started Task:4  at  13:47:29 processing 400  objects
Started Task:5  at  13:47:29 processing 400  objects
Started Task:6  at  13:47:29 processing 400  objects
Started Task:7  at  13:47:29 processing 400  objects
Received Task:  1  at  13:47:44 with SY-SUBRC =0  on return
Started Task:1  at  13:47:44 processing 400  objects
Received Task:  2  at  13:47:48 with SY-SUBRC =0  on return
Started Task:2  at  13:47:48 processing 400  objects
Received Task:  5  at  13:48:02 with SY-SUBRC =0  on return
Started Task:5  at  13:48:02 processing 400  objects
Received Task:  6  at  13:48:03 with SY-SUBRC =0  on return
Started Task:6  at  13:48:03 processing 400  objects
Received Task:  7  at  13:48:04 with SY-SUBRC =0  on return
Started Task:7  at  13:48:04 processing 400  objects
Received Task:  4  at  13:48:05 with SY-SUBRC =0  on return
Started Task:4  at  13:48:05 processing 400  objects
Received Task:  3  at  13:48:09 with SY-SUBRC =0  on return
Started Task:3  at  13:48:10 processing 400  objects
Received Task:  1  at  13:48:39 with SY-SUBRC =0  on return
Started Task:1  at  13:48:39 processing 400  objects
Received Task:  2  at  13:48:52 with SY-SUBRC =

0  on return

Started Task:5  at  13:49:33 processing 400  objects
Received Task:  4  at  13:49:38 with SY-SUBRC =0  on return
Started Task:4  at  13:49:38 processing 400  objects
Received Task:  3  at  13:49:41 with SY-SUBRC =0  on return
Started Task:3  at  13:49:41 processing 400  objects
Received Task:  6  at  13:50:26 with SY-SUBRC =0  on return
Started Task:6  at  13:50:27 processing 400  objects
Received Task:  1  at  13:50:27 with SY-SUBRC =0  on return
Started Task:1  at  13:50:27 processing 400  objects
Received Task:  2  at  13:50:38 with SY-SUBRC =0  on return
Started Task:2  at  13:50:38 processing 400  objects
Received Task:  7  at  13:50:39 with SY-SUBRC =0  on return
Started Task:7  at  13:50:39 processing 400  objects
Received Task:  1  at  13:51:02 with SY-SUBRC =0  on return
Started Task:1  at  13:51:02 processing 400  objects
Received Task:  5  at  13:51:35 with SY-SUBRC =0  on return
Started Task:5  at  13:51:35 processing 400  objects
Received Task:  1  at  13:51:38 with SY-SUBRC =0  on return
Started Task:1  at  13:51:38 processing 400  objects
Received Task:  5  at  13:51:44 with SY-SUBRC =0  on return
Started Task:5  at  13:51:44 processing 400  objects
Received Task:  1  at  13:51:54 with SY-SUBRC =0  on return
Started Task:1  at  13:51:54 processing 400  objects
Received Task:  7  at  13:52:10 with SY-SUBRC =0  on return
Started Task:7  at  13:52:10 processing 400  objects
Received Task:  5  at  13:53:01 with SY-SUBRC =0  on return
Started Task:5  at  13:53:01 processing 400  objects
Received Task:  6  at  13:53:03 with SY-SUBRC =0  on return
Started Task:6  at  13:53:04 processing 400  objects
Received Task:  4  at  13:53:25 with SY-SUBRC =0  on return

04.03.2016Parallel Processing of the Generation of ABAP Loads     2
Started Task:2  at  13:48:52 processing 400  objects
Received Task:  6  at  13:49:29 with SY-SUBRC =0  on return
Sriram2009
Active Contributor
0 Kudos

Hi Singh.

1. SAP system kernel level is very old. you have to upgrade the kernel from NW 7.00 level 146 to 7.20 ext version based on SAP Basis SP level.

Refer the SAP Note

1636252 - Installing a 7.20 kernel in SAP Web AS 7.00/7.01/7.10/7.11

2. After that start the SGEN.

Regards

SS

Former Member
0 Kudos

Hi,

Please go through below sapnotes

865759 - GEN_FRAGVIEW_EMPTY when customer include is empty

Regards,

Prithviraj.