Dear All,

The in-process inspection lot where the usage decision is accepted and lot has been cancelled unfortunately . Due to this the Production order closing cannot be completed .

please do provide the solution how to reverse the usage Decision and Status Reset for the same inspection lot .

The Error Displaye "inspection Lot "XXXX"for order "XXXX" does not have required status.

Please do provide solution for closing the production order.

Thanks and Regards.