Hi Guys,

As far as I know, in SRM 5.0 we use DNL_CUST_BASIS3 object for transferring UOMs. Is it still valid in SRM 7.0 ?  We have several UOMs in ECC that we need to sync with SRM 7.0.  Can someone please provide input ?

Thank you

Srini J

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Anil,

Please check.

Best Regards,

Siddappa

moacir_goelzer
Explorer
0 Kudos

Hi Anil,

Regarding the SAP note 872533 the DNL_CUST_BASIS3 is active to downloading the units of measure (UoM) and currencies.

Thank you,

Moacir

Former Member
0 Kudos

Hi Srini,

Yes, It is required to run the object DNL_CUST_BASIS3 to get the UOM sync from ECC to SRM.

Please run this object as a initial load in R3AS.

Recently we had this UOM issue. After running the DNL_CUST_BASIS we resolved the problem.

Thanks & regards,

Anil

Former Member
0 Kudos

Hi Anil

Thanks for your response. I thought this object is obsolete in SRM 7.0. I'll run it as suggested.

Thanks again.  

Kind regards