Hi Experts,

I have a issue with PO available dates in R/3 and APO.

Exmple: PO Avail date in R/3 02.05.2016 and in  APO 28.04.2016(Delivery Time 23:59:59)

In my case while coming holidays or weekends APO dates are coming back.It means the date in R/3 is Monday and in APO it comes back to Friday.

Please help on this issue

Thanks ,

Vasu

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Vasu

Can you go through the Note 333386 - Availability date different in APO and R/3

I think this would provide you some clues about the problem.